CT2 to increase Hamad Port’s capacity to 5 million TEUs

Published: 29 Jul 2021 - 08:30 am | Last Updated: 01 Nov 2021 - 02:31 pm

The Peninsula

Doha: Container Terminal 2 (CT2) at Hamad Port will increase the port’s capacity to 5 million TEUs (twenty-foot equivalent units) annually upon completion of the development process. 

And CT2 will have the optimum capacity of 2.5 million TEUs upon completion of all phases, Mwani Qatar said on its Tweeter yesterday.  

“Hamad Port’s CT2 is designed to address the increasing trade volume, enhancing ease of doing business in Qatar as well as supporting the achievement of economic diversification, which is one of the most important goals of QNV2030,” it said. 

The 403,500sqm CT2 development project comprises four phases. Full operation of Phases 1 and 2 will start before the end of 2022. Phases 3 and 4 will be developed later to raise the port’s operational capacity according to local market’s needs. 

The area of Phases 1 and 2 of Hamad Port’s CT2 is 380,000sqm. Its quay is 624m long. The Phase 1 of CT2 has been equipped with three STS (ship-to-shore) quay cranes with advanced technology, including semi-automation and remote-control operations. STS cranes are fast and highly efficient in handling containers and capable of handling latest types of vessels.